| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-11 | ZAPATA Z-1 AISLADA DE 1.20X1.95M POR 25CM DE PERALTE, A BASE DE CONCRETO F'C=200KG/CM2, ARMADO CON 5 VARILLAS DEL No.5 EN SENTIDO LARGO Y 9 VAR. No.5 EN SENTIDO CORTO, INCLUYE CIMBRA Y DESCIMBRA, ESCUADRAS, Y DESPERDICIOS, COLADO, NIVELADO, VIBRADO, CURADO, ACARREOS, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.393000 | $80.00 | $31.44 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.120000 | $11.00 | $1.32 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 2.800000 | $5.00 | $14.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 1.000000 | $10.00 | $10.00 |
| ACERO 05 | ACERO DEL No. 5 | KG | 38.470000 | $6.00 | $230.82 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.800000 | $10.43 | $8.34 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.643500 | $824.77 | $530.74 |
| Suma de Material | $826.66 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.050000 | $176.48 | $8.82 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.270000 | $448.80 | $121.18 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.220000 | $448.80 | $98.74 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.053000 | $1,094.57 | $58.01 |
| Suma de Mano de Obra | $286.75 | ||||
| Costo Directo | $1,113.41 |