| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-07 | ZAPATA Z-2 AISLADA DE 3.00X2.00M POR 35CM DE PERALTE, A BASE DE CONCRETO F'C=200KG/CM2, ARMADO CON VARILLAS DEL No.5 A CADA 12CM EN SENTIDO LARGO Y A CADA 20CM EN SENTIDO CORTO, INCLUYE CIMBRA Y DESCIMBRA, ESCUADRAS, Y DESPERDICIOS, COLADO, NIVELADO, VIBRADO, CURADO, ACARREOS, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 2.310000 | $723.12 | $1,670.41 |
| ACERO 05 | ACERO DEL No. 5 | KG | 144.000000 | $6.00 | $864.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.400000 | $5.00 | $17.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.762500 | $80.00 | $61.00 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 2.310000 | $723.12 | $1,670.41 |
| ACERO 05 | ACERO DEL No. 5 | KG | 144.000000 | $6.00 | $864.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.400000 | $5.00 | $17.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.762500 | $80.00 | $61.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.700000 | $11.00 | $18.70 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 2.000000 | $10.00 | $20.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.700000 | $11.00 | $18.70 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 2.000000 | $10.00 | $20.00 |
| Suma de Material | $5,302.21 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.175000 | $1,094.57 | $191.55 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.500000 | $448.80 | $224.40 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.960000 | $448.80 | $430.85 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.175000 | $1,094.57 | $191.55 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.500000 | $448.80 | $224.40 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.960000 | $448.80 | $430.85 |
| Suma de Mano de Obra | $1,693.60 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 2.000000 | $15.98 | $31.96 |
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 2.000000 | $15.98 | $31.96 |
| Suma de Equipo | $63.92 | ||||
| Costo Directo | $7,059.73 |