| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-D1 | TRABE DE CONCRETO F'C=200 KG/CM2 ARMADO DE 2.70X0.30 ARMADO CON 2 V'S No. 3 (LECHO SUPERIOR) MAS 2 V'S No. 4 CORRIDAS Y 2 BASTONES No. 3 (LECHO INFERIOR), INCLUYE CIMBRA,DESCIMBRADO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.891000 | $723.12 | $644.30 |
| ACERO 03 | ACERO DEL # (3/) | KG | 18.320000 | $6.00 | $109.92 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 0.700000 | $5.00 | $3.50 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 1.450000 | $80.00 | $116.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 2.000000 | $10.00 | $20.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.040000 | $10.43 | $0.42 |
| Suma de Material | $895.24 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.500000 | $440.17 | $220.09 |
| Suma de Mano de Obra | $220.09 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.400000 | $15.98 | $6.39 |
| Suma de Equipo | $6.39 | ||||
| Costo Directo | $1,121.71 |