| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-21 | REPIZON DE 15-30X20CM DE CONCRETO HIDRAULICO F'C=200 KG/CM2, ARMADO CON 4 VARILLAS DE 3/8'' Y ESTRIBOS DEL No.2 A CADA 15CM, CIMBRA Y DESCIMBRA, VIBRADO CURADO, EL PRECIO UNITARIO INCLUYE: MATERIALES, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.058000 | $723.12 | $41.94 |
| ACERO 03 | ACERO DEL # (3/) | KG | 2.670000 | $6.00 | $16.02 |
| ACERO-022 | ALAMBRON | KG | 1.650000 | $6.00 | $9.90 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 0.700000 | $5.00 | $3.50 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.110000 | $80.00 | $8.80 |
| CIMBRA-011 | CHAFLAN DE 1" | ML | 2.000000 | $4.00 | $8.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.250000 | $10.00 | $2.50 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.040000 | $10.43 | $0.42 |
| Suma de Material | $92.18 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.200000 | $440.17 | $88.03 |
| Suma de Mano de Obra | $88.03 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.98 | $1.60 |
| Suma de Equipo | $1.60 | ||||
| Costo Directo | $181.81 |