| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IEF-04 | CABLE THW No.250 MCM, CONDUMEX TRES HILOS, INCLUYE MATERIAL, MANO DE OBRA Y HERRAMIENTA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=100 H/O | Concreto hecho en obra f'c = 100 kg/cm2agregado max. 3/4" R.N. | M3 | 0.065230 | $599.66 | $39.12 |
| CABLE THWN CAL250MCM | CABLE THWN CAL250MCM | ML | 3.090000 | $84.00 | $259.56 |
| Suma de Material | $298.68 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | Jor | 0.066670 | $667.60 | $44.51 |
| Suma de Mano de Obra | $44.51 | ||||
| Herramienta | |||||
| MIC-01* | MATER. MISCELANEOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $343.18 |