| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-E1 | ZAPATA DE CONCRETO ARMADO F'C= 200KG/CM2 DE 0.80*0.80 MTS DE 20 CM DE PERALTE ARMADA CON 4 VARILLAS DEL NO 4 EN AMBOS SENTIDOS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.160000 | $80.00 | $12.80 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.200000 | $11.00 | $2.20 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 2.800000 | $5.00 | $14.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| ACERO 04 | ACERO DEL No. 4 | KG | 7.650000 | $6.00 | $45.90 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.400000 | $10.43 | $4.17 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.140800 | $824.77 | $116.13 |
| CONCRETO 01 | BOMBA PARA CONCRETO PREMEZCLADA | M3 | 0.140800 | $100.00 | $14.08 |
| Suma de Material | $214.28 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.050000 | $176.48 | $8.82 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.055000 | $448.80 | $24.68 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.091000 | $448.80 | $40.84 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.017000 | $1,094.57 | $18.61 |
| Suma de Mano de Obra | $92.96 | ||||
| Costo Directo | $307.24 |