| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-12 A | ESCALONES DE CONCRETO F'C=200KG/CM2 DE 35CM DE HUELLA Y PERALTE DE 15CM | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.150000 | $80.00 | $12.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.500000 | $11.00 | $5.50 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.000000 | $5.00 | $5.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.100000 | $10.00 | $1.00 |
| ACERO 04 | ACERO DEL No. 4 | KG | 2.000000 | $6.00 | $12.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.060000 | $10.43 | $0.63 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.028000 | $824.77 | $23.09 |
| Suma de Material | $59.22 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.020000 | $176.48 | $3.53 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.020000 | $448.80 | $8.98 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.100000 | $448.80 | $44.88 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.010000 | $1,094.57 | $10.95 |
| Suma de Mano de Obra | $68.33 | ||||
| Costo Directo | $127.55 |