| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESTR-13 | ESCALONES DE CONCRETO HIDRAULICO F'C=250KG/CM2 DE 1.25M DE ANCHO POR 30CM DE HUELLA Y 17CM DE PERALTE, QUE COMUNICA A LA RAMPA DE ACCESO DE LA TORRE, ACABADO SERROTEADO, EL PRECIO UNITARIO INCLUYE: MATERIALES, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PREM 250 | concreto premezclado f'c=250 kg/cm2 | m3 | 0.082600 | $886.41 | $73.22 |
| CONCRETO 01 | BOMBA PARA CONCRETO PREMEZCLADA | M3 | 0.082600 | $100.00 | $8.26 |
| ACERO 03 | ACERO DEL # (3/) | KG | 1.300000 | $6.00 | $7.80 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 0.600000 | $5.00 | $3.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.100000 | $80.00 | $8.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.100000 | $10.00 | $1.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.080000 | $10.43 | $0.83 |
| Suma de Material | $103.21 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.020000 | $1,094.57 | $21.89 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.200000 | $448.80 | $89.76 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.030000 | $448.80 | $13.46 |
| Suma de Mano de Obra | $125.12 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.050000 | $15.98 | $0.80 |
| Suma de Equipo | $0.80 | ||||
| Costo Directo | $229.13 |