| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-02 A | BASE Y MURETES (DE CANAL) DE CONCRETO F'C=200KG/CM2 DE 10CM DE ESPESOR, ARMADO CON VARILLAS DEL No.4 (1/2'') A CADA 25CM AMBOS SENTIDOS, ACABADO PULIDO, JUNTA FRIA PARA MODULACION DE 3.00M, COLADO, VIBRADO, NIVELACION Y CURADO, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, MANO DE OBRA Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.110000 | $723.12 | $79.54 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.110000 | $723.12 | $79.54 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.110000 | $723.12 | $79.54 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $5.00 | $6.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $5.00 | $6.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $5.00 | $6.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.500000 | $80.00 | $40.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.500000 | $80.00 | $40.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.500000 | $80.00 | $40.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.250000 | $10.00 | $2.50 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.250000 | $10.00 | $2.50 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.250000 | $10.00 | $2.50 |
| ACERO 04 | ACERO DEL No. 4 | KG | 8.000000 | $6.00 | $48.00 |
| ACERO 04 | ACERO DEL No. 4 | KG | 8.000000 | $6.00 | $48.00 |
| ACERO 04 | ACERO DEL No. 4 | KG | 8.000000 | $6.00 | $48.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.060000 | $10.43 | $0.63 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.060000 | $10.43 | $0.63 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.060000 | $10.43 | $0.63 |
| Suma de Material | $533.31 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.300000 | $440.17 | $132.05 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.300000 | $440.17 | $132.05 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.300000 | $440.17 | $132.05 |
| Suma de Mano de Obra | $396.15 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.200000 | $15.98 | $3.20 |
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.200000 | $15.98 | $3.20 |
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.200000 | $15.98 | $3.20 |
| Suma de Equipo | $9.59 | ||||
| Costo Directo | $939.05 |