| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-D5 | TRABES DE CONCRETO ARMADO F'C=200 KG/CM2 DE 0.25X0.35X7.00 MTS., ARMADA CON 2 V'S # 4 TODO LO LARGO + 2 BASTONES V'S # 4 AL CENTRO (LECHO SUPERIOR) Y 2 V'S #4 EN EL LECHO INFERIOR, ESTRIBOS #3 A CADA 15 CM. INCLUYE CIMBRA, DESCIBRA, HABILITADO DEL ACERO, COLADO, MATERIAL, MANO DE OBRA Y HERRAMIENTA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.250000 | $80.00 | $20.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 2.500000 | $11.00 | $27.50 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 10.000000 | $5.00 | $50.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.125000 | $10.00 | $1.25 |
| ACERO 04 | ACERO DEL No. 4 | KG | 13.610000 | $6.00 | $81.66 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.408500 | $10.43 | $4.26 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.096000 | $824.77 | $79.18 |
| CONCRETO 01 | BOMBA PARA CONCRETO PREMEZCLADA | M3 | 0.096000 | $100.00 | $9.60 |
| ADITIVO-01 | IMPERMEABILIZANTE INTEGRAL | KG* | 10.000000 | $5.00 | $50.00 |
| ADITIVO-02 | FIBRA DE POLIPROPILENO | M3* | 0.250000 | $60.00 | $15.00 |
| Suma de Material | $338.45 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.020000 | $176.48 | $3.53 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.180000 | $448.80 | $80.78 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.300000 | $448.80 | $134.64 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.019000 | $1,094.57 | $20.80 |
| Suma de Mano de Obra | $239.75 | ||||
| Costo Directo | $578.20 |