| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-08. | SISTEMA DE LOSA A BASE DE NERVADURAS, CASETON DE POLIESTIRENO Y TRABES, INCLUYE: MALLA ELECTROSOLDADA 6X6/10-10, CIMBRA PERIMETRAL, OBRA FALSA PARA APUNTALAMIENTO, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CASETON | CASETON DE POLIESTIRENO 40*40*25 | PZA | 4.000000 | $16.00 | $64.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.200000 | $80.00 | $16.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.400000 | $5.00 | $17.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CONCRETO 01 | BOMBA PARA CONCRETO PREMEZCLADA | M3 | 0.100000 | $100.00 | $10.00 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.100000 | $824.77 | $82.48 |
| Suma de Material | $190.58 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.040000 | $1,094.57 | $43.78 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.120000 | $448.80 | $53.86 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.080000 | $448.80 | $35.90 |
| Suma de Mano de Obra | $133.54 | ||||
| Costo Directo | $324.12 |