| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-29-04* | CARACAMO DE CONCRETO EN FONDO DE 0.60X0.60X0.60 M , ARMADO CON UNA PARRILLA CON VARILLAS DEL N0 3 A CADA 20 CM EN AMBOS SENTIDOS, | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.430600 | $723.12 | $311.38 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.430600 | $723.12 | $311.38 |
| ACERO 03 | ACERO DEL # (3/) | KG | 17.220000 | $6.00 | $103.32 |
| ACERO 03 | ACERO DEL # (3/) | KG | 17.220000 | $6.00 | $103.32 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 2.300000 | $5.00 | $11.50 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 2.300000 | $5.00 | $11.50 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.000000 | $11.00 | $11.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.000000 | $11.00 | $11.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.350000 | $80.00 | $28.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.350000 | $80.00 | $28.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.200000 | $10.43 | $2.09 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.200000 | $10.43 | $2.09 |
| Suma de Material | $944.56 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.047000 | $1,094.57 | $51.44 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.047000 | $1,094.57 | $51.44 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.410000 | $448.80 | $184.01 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.410000 | $448.80 | $184.01 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.280000 | $448.80 | $125.66 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.280000 | $448.80 | $125.66 |
| Suma de Mano de Obra | $722.23 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.500000 | $15.98 | $7.99 |
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.500000 | $15.98 | $7.99 |
| Suma de Equipo | $15.98 | ||||
| Costo Directo | $1,682.78 |