| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-03. | CADENA DE CERRAMIENTO 20X20CM DE CONCRETO HIDRAULICO F'C=200 KG/CM2, ARMADO CON 4 VARILLAS DEL No. 4 Y ESTRIBOS DEL No.3 A CADA 15CM, CIMBRA Y DESCIMBRA, VIBRADO, CURADO, ACARREOS LOCALES, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.150000 | $80.00 | $12.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.000000 | $5.00 | $5.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.250000 | $11.00 | $2.75 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.020000 | $10.43 | $0.21 |
| ACERO 03 | ACERO DEL # (3/) | KG | 3.110000 | $6.00 | $18.66 |
| ACERO 04 | ACERO DEL No. 4 | KG | 4.780000 | $6.00 | $28.68 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.120000 | $10.00 | $1.20 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.044000 | $723.12 | $31.82 |
| Suma de Material | $100.32 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.180000 | $440.17 | $79.23 |
| Suma de Mano de Obra | $79.23 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.98 | $1.60 |
| Suma de Equipo | $1.60 | ||||
| Costo Directo | $181.14 |