| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-23* | ZAPATA Z-1 AISLADA DE 2,50X4,50M POR 30CM DE PERALTE, A BASE DE CONCRETO F'C=200KG/CM2, ARMADO CON VAR. No.4 A CADA 20CM AMBOS SENTIDOS INCLUYE CIMBRA Y DESCIMBRA, ESCUADRAS, Y DESPERDICIOS, COLADO, NIVELADO, VIBRADO, CURADO, ACARREOS, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 3.710000 | $723.12 | $2,682.78 |
| ACERO 04 | ACERO DEL No. 4 | KG | 134.460000 | $6.00 | $806.76 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 2.300000 | $5.00 | $11.50 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.000000 | $11.00 | $11.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 1.050000 | $80.00 | $84.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 1.000000 | $10.00 | $10.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.400000 | $10.43 | $4.17 |
| Suma de Material | $3,610.21 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.371000 | $1,094.57 | $406.09 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.525000 | $448.80 | $235.62 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 1.000000 | $448.80 | $448.80 |
| Suma de Mano de Obra | $1,090.51 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 1.000000 | $15.98 | $15.98 |
| Suma de Equipo | $15.98 | ||||
| Costo Directo | $4,716.69 |