| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-40-1 | BARRA DE CONCRETO ARMADO F'c=150 KG/CM2 DE 10 CM DE ESPESOR DE 0.80X6.00 M. ARMADA CON VARILLAS DEL No. 3 EN AMBOS SENTIDOS,INCLUYE CIMBRA DESCIMBRA MATERIAL Y MANO DE OBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO H/O 150 | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.052800 | $670.81 | $35.42 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 0.300000 | $5.00 | $1.50 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.070000 | $80.00 | $5.60 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| ACERO 03 | ACERO DEL # (3/) | KG | 3.850000 | $6.00 | $23.10 |
| Suma de Material | $66.72 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.250000 | $440.17 | $110.04 |
| Suma de Mano de Obra | $110.04 | ||||
| Costo Directo | $176.76 |