| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-12 | ZAPATA Z-2 AISLADA DE 1.50X2.10M POR 25CM DE PERALTE, A BASE DE CONCRETO F'C=200KG/CM2, ARMADO CON 6 VARILLAS DEL No.5 EN SENTIDO LARGO Y 9 VAR. No.5 EN SENTIDO CORTO, INCLUYE CIMBRA Y DESCIMBRA, ESCUADRAS, Y DESPERDICIOS, COLADO, NIVELADO, VIBRADO, CURADO, ACARREOS, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.450000 | $80.00 | $36.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.300000 | $11.00 | $3.30 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.000000 | $5.00 | $15.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 1.200000 | $10.00 | $12.00 |
| ACERO 05 | ACERO DEL No. 5 | KG | 48.860000 | $6.00 | $293.16 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.500000 | $10.43 | $5.22 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.866200 | $824.77 | $714.42 |
| Suma de Material | $1,079.09 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.070000 | $176.48 | $12.35 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.349000 | $448.80 | $156.63 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.230000 | $448.80 | $103.22 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.080000 | $1,094.57 | $87.57 |
| Suma de Mano de Obra | $359.77 | ||||
| Costo Directo | $1,438.87 |