| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-06. | CONTRATRABES DE CIMENTACION DE CONCRETO HIDRAULICO F'C=200KG/CM2 DE B=20XH=40CMS., ARMADO CON 8 VARILLAS DEL No.4 Y ESTRIBOS DEL No3 @15 CMS., INCLUYE: CIMBRA Y DESCIMBRA ACABADO COMUN, EL PRECIO UNITARIO INCLUYE: MATERIALES, MANO DE OBRA Y HERRAMIENTA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.096000 | $723.12 | $69.42 |
| CIMBRA-011 | CHAFLAN DE 1" | ML | 2.000000 | $4.00 | $8.00 |
| ACERO 03 | ACERO DEL # (3/) | KG | 4.500000 | $6.00 | $27.00 |
| ACERO 04 | ACERO DEL No. 4 | KG | 9.560000 | $6.00 | $57.36 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.400000 | $5.00 | $17.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.200000 | $11.00 | $2.20 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.250000 | $80.00 | $20.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 1.000000 | $10.00 | $10.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.100000 | $10.43 | $1.04 |
| Suma de Material | $212.02 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.010000 | $1,094.57 | $10.95 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.130000 | $448.80 | $58.34 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.100000 | $448.80 | $44.88 |
| Suma de Mano de Obra | $114.17 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.98 | $1.60 |
| Suma de Equipo | $1.60 | ||||
| Costo Directo | $327.79 |