| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-20 A | MESETA DE CONCRETO F'C=150 KG/CM2 DE 3.10X0.60X0.10 MTS ARMADA CON V'S DEL NO. 3 EN AMBOS SENTIDOS, INCLUYE CIMBRA,DESCIMBRA, HABILITADO DE ACERO, COLADO, MATERIALES MANO DE OBRA Y HERRAMIENTA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO H/O 150 | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.204600 | $670.81 | $137.25 |
| ACERO 03 | ACERO DEL # (3/) | KG | 26.460000 | $6.00 | $158.76 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 2.300000 | $5.00 | $11.50 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.500000 | $11.00 | $5.50 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.300000 | $80.00 | $24.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.120000 | $10.00 | $1.20 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.040000 | $10.43 | $0.42 |
| Suma de Material | $338.62 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.500000 | $440.17 | $220.09 |
| Suma de Mano de Obra | $220.09 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.98 | $1.60 |
| Suma de Equipo | $1.60 | ||||
| Costo Directo | $560.31 |