| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-D1 | FIRME DE CONCRETO F'C=250 KG/CM2 DE 20CM DE ESPESOR (CON IMPERMEABILIZANTE INTEGRAL AL 1.5% Y FIBRA DE POLIPROPILENO), ARMADA CON DOBLE PARRILLA DE VARILAS DEL No 4 A CADA 15 CM DE ESPESOR EN AMBOS SENTIDOS, INCLUYE: CIMBRA, DESCIMBRA, HABILITADO DE ACERO, COLADO, CURADO DE CONCRETO, MATERIALES MANO DE OBRA Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.050000 | $80.00 | $4.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.250000 | $11.00 | $2.75 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.000000 | $5.00 | $5.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.120000 | $10.00 | $1.20 |
| ACERO 04 | ACERO DEL No. 4 | KG | 26.550000 | $6.00 | $159.30 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.790000 | $10.43 | $8.24 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.210000 | $824.77 | $173.20 |
| CONCRETO 01 | BOMBA PARA CONCRETO PREMEZCLADA | M3 | 0.210000 | $100.00 | $21.00 |
| ADITIVO-01 | IMPERMEABILIZANTE INTEGRAL | KG* | 20.000000 | $5.00 | $100.00 |
| ADITIVO-02 | FIBRA DE POLIPROPILENO | M3* | 0.250000 | $60.00 | $15.00 |
| Suma de Material | $489.69 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.020000 | $176.48 | $3.53 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.300000 | $448.80 | $134.64 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.250000 | $448.80 | $112.20 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.035000 | $1,094.57 | $38.31 |
| Suma de Mano de Obra | $288.68 | ||||
| Costo Directo | $778.37 |