| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| D-IE-07 | ALIMENTACION ELECTRICA AL TABLERO "ALM" DESDE TABLERO DE DISTRIBUCION DE SUBESTACION ELECTRICA, INCLUYE: 2 TUBOS DE PVC DE 2'' TIPO PESADO, ENCOFRADO DE CONCRETO F'C=100KG/CM2, 3 HILOS DE CABLE THW CAL.6, 1 HILO DE CABLE THW CAL.8, 1 HILO DE CABLE THW CA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.PVC TP 50 MM | TUBO C.PVC TP 50 MM | ML | 2.000000 | $20.74 | $41.48 |
| PEGAMENTO PVC | PEGAMENTO PVC | BOTE | 0.020000 | $87.99 | $1.76 |
| CABLE CU DESN. # 10 | CABLE CU DESN. # 10 | ML | 1.050000 | $2.11 | $2.22 |
| CABLE THWN CAL. 6 | CABLE THWN CAL. 6 | Ml | 3.150000 | $9.50 | $29.93 |
| CABLE THWN CAL. 8 | CABLE THWN CAL. 8 | ML | 1.050000 | $4.24 | $4.45 |
| CONCRETO F-C=100 H/O | Concreto hecho en obra f'c = 100 kg/cm2agregado max. 3/4" R.N. | M3 | 0.065230 | $599.66 | $39.12 |
| Suma de Material | $118.95 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | Jor | 0.200000 | $667.60 | $133.52 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.040000 | $440.17 | $17.61 |
| Suma de Mano de Obra | $151.13 | ||||
| Costo Directo | $270.07 |