| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HER-17 | TAPANCO DE PERFILES MONTEN DE 10'' X 3 1/2'' CAL.14, INCLUYE: PISO DE MONTEN, VIGAS Y COLUMNAS TUBULAR FORMADO POR 2 PERFILES MONTEN, SOLDADURA, PRIMER ANTICORROSIVO, PINTURA ESMALTE 2 MANOS, ACARREOS LOCALES Y ELEVACION, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| HERRERIA-04 | VIGUETA TIPO " I " | ML | 0.750000 | $354.00 | $265.50 |
| HERRERIA-05 | MONTEN DE 8 | ML | 4.000000 | $74.57 | $298.28 |
| PINTURA-01 | PINTURA DE ESMALTE COMEX 100 | LT | 0.250000 | $60.00 | $15.00 |
| PINTURA-05 | PRIMARIO ANTICORROSIVO | LT | 0.125000 | $49.00 | $6.13 |
| PINTURA-06 | THINNER | LT. | 0.200000 | $16.50 | $3.30 |
| Suma de Material | $588.21 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 22 | (1 OF. Herrero+1 AYUD.) | Jor | 0.250000 | $448.80 | $112.20 |
| CUADRILLA NO. 18 | (1 Of. Pintor +2 Ayudante). | Jor | 0.030000 | $587.91 | $17.64 |
| Suma de Mano de Obra | $129.84 | ||||
| Equipo | |||||
| MAQ. SOLDAR EST. | Soldadora Miller Dimension Mod. 652 | HR | 8.000000 | $6.75 | $54.00 |
| Suma de Equipo | $54.00 | ||||
| Costo Directo | $772.04 |