| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-05. | DADO DE 45x45CM POR 90CM DE ALTURA, A BASE DE CONCRETO F'C=200KG/CM2, ARMADO CON 8 VARILLAS DEL No.5 (EMPAQUETADOS DE DOS EN DOS) + 1 VARILLA DEL No.4 EN CADA CARAY ESTRIBOS Y GRAPAS DEL No.3 (3/8'') A CADA 15CM, INCLUYE CIMBRA Y DESCIMBRA, ESCUADRAS, GANCHOS Y DESPERDICIOS, COLADO, NIVELADO, VIBRADO, CURADO, ACARREOS, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.405000 | $80.00 | $32.40 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.000000 | $11.00 | $11.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 4.300000 | $5.00 | $21.50 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| ACERO 04 | ACERO DEL No. 4 | KG | 14.610000 | $6.00 | $87.66 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 4.380000 | $10.43 | $45.68 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO DE F`C=200 KG/CM2 | M3 | 0.222700 | $824.77 | $183.68 |
| Suma de Material | $386.92 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.050000 | $176.48 | $8.82 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.100000 | $448.80 | $44.88 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.200000 | $448.80 | $89.76 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.040000 | $1,094.57 | $43.78 |
| Suma de Mano de Obra | $187.25 | ||||
| Costo Directo | $574.17 |