| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESTR-08 | LOSA DE CONCRETO F'C=250KG/CM2 DE 12CM ESPESOR, ARMADO CON VAR. #3 (3/8'') A CADA 15CM AMBOS SENTIDOS, BALLONETAS DE 1.50M DE DESARROLLO A CADA 40CM DE VARILLA 3/8'', CIMBRA Y DESCIMBRA, COLADO, VIBRADO, NIVELADO, CURADO, ACARREOS Y ELEVACION, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PREM 250 | concreto premezclado f'c=250 kg/cm2 | m3 | 0.132000 | $886.41 | $117.01 |
| CONCRETO PREM 250 | concreto premezclado f'c=250 kg/cm2 | m3 | 0.132000 | $886.41 | $117.01 |
| CONCRETO PREM 250 | concreto premezclado f'c=250 kg/cm2 | m3 | 0.132000 | $886.41 | $117.01 |
| CONCRETO 01 | BOMBA PARA CONCRETO PREMEZCLADA | M3 | 0.132000 | $100.00 | $13.20 |
| CONCRETO 01 | BOMBA PARA CONCRETO PREMEZCLADA | M3 | 0.132000 | $100.00 | $13.20 |
| CONCRETO 01 | BOMBA PARA CONCRETO PREMEZCLADA | M3 | 0.132000 | $100.00 | $13.20 |
| ACERO 03 | ACERO DEL # (3/) | KG | 9.000000 | $6.00 | $54.00 |
| ACERO 03 | ACERO DEL # (3/) | KG | 9.000000 | $6.00 | $54.00 |
| ACERO 03 | ACERO DEL # (3/) | KG | 9.000000 | $6.00 | $54.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 4.200000 | $5.00 | $21.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 4.200000 | $5.00 | $21.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 4.200000 | $5.00 | $21.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.400000 | $11.00 | $4.40 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.400000 | $11.00 | $4.40 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.400000 | $11.00 | $4.40 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.250000 | $80.00 | $20.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.250000 | $80.00 | $20.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.250000 | $80.00 | $20.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.080000 | $10.43 | $0.83 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.080000 | $10.43 | $0.83 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.080000 | $10.43 | $0.83 |
| Suma de Material | $706.32 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.015000 | $1,094.57 | $16.42 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.015000 | $1,094.57 | $16.42 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.015000 | $1,094.57 | $16.42 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.140000 | $448.80 | $62.83 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.140000 | $448.80 | $62.83 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.140000 | $448.80 | $62.83 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.065000 | $448.80 | $29.17 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.065000 | $448.80 | $29.17 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.065000 | $448.80 | $29.17 |
| Suma de Mano de Obra | $325.27 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.98 | $1.60 |
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.98 | $1.60 |
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.98 | $1.60 |
| Suma de Equipo | $4.79 | ||||
| Costo Directo | $1,036.38 |