| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-17. | COLUMNA C1 DE CONCRETO F'C=200KG/CM2 DE 40x40CM, ARMADO CON 8 VARILLAS DEL No.5 (EMPAQUETADOS DE DOS EN DOS ESQUINAS) + 1 VARILLAS DEL No. 4 EN CADA CARA Y ESTRIBOSY DOS GRAPAS DEL No.3 A CADA 15CM, CIMBRA Y DESCIMBRA ACABADO APARENTE, VIBRADO, CURADO, ACARREOS LOCALES, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.400000 | $80.00 | $32.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.000000 | $5.00 | $5.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.250000 | $11.00 | $2.75 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.200000 | $10.43 | $2.09 |
| ACERO 03 | ACERO DEL # (3/) | KG | 6.680000 | $6.00 | $40.08 |
| ACERO 04 | ACERO DEL No. 4 | KG | 4.780000 | $6.00 | $28.68 |
| ACERO 05 | ACERO DEL No. 5 | KG | 14.970000 | $6.00 | $89.82 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.120000 | $10.00 | $1.20 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.168000 | $723.12 | $121.48 |
| Suma de Material | $323.10 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.220000 | $440.17 | $96.84 |
| Suma de Mano de Obra | $96.84 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.300000 | $15.98 | $4.79 |
| Suma de Equipo | $4.79 | ||||
| Costo Directo | $424.73 |