| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-04. | ZAPATA AISLADA Z1, Z3, Z4, Z5, Z6 Y Z7 DE 20CM DE PERALTE, A BASE DE CONCRETO F'C=200KG/CM2, ARMADO CON VARILLAS DEL No.4 A CADA 17CM AMBOS SENTIDOS, INCLUYE CIMBRA Y DESCIMBRA, ESCUADRAS, Y DESPERDICIOS, COLADO, NIVELADO, VIBRADO, CURADO, ACARREOS, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, ANDAMIO, MANO DE OBRA Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.220000 | $723.12 | $159.09 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.220000 | $723.12 | $159.09 |
| ACERO 04 | ACERO DEL No. 4 | KG | 14.060000 | $6.00 | $84.36 |
| ACERO 04 | ACERO DEL No. 4 | KG | 14.060000 | $6.00 | $84.36 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $5.00 | $6.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $5.00 | $6.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.200000 | $80.00 | $16.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.200000 | $80.00 | $16.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.200000 | $11.00 | $2.20 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.200000 | $11.00 | $2.20 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| Suma de Material | $545.29 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.001000 | $1,094.57 | $1.09 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.001000 | $1,094.57 | $1.09 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.125000 | $448.80 | $56.10 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.125000 | $448.80 | $56.10 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.100000 | $448.80 | $44.88 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.100000 | $448.80 | $44.88 |
| Suma de Mano de Obra | $204.15 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.500000 | $15.98 | $7.99 |
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.500000 | $15.98 | $7.99 |
| Suma de Equipo | $15.98 | ||||
| Costo Directo | $765.42 |