| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A-6 | ACERO DE REFUERZO Fy=4200 KG/CM2, EN CIMENTACION. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO VARIOS D | ACERO DE REFUERZO DE DIFERENTES DIAMETROS | KG | 1.200000 | $11.00 | $13.20 |
| ACERO VARIOS D | ACERO DE REFUERZO DE DIFERENTES DIAMETROS | KG | 1.200000 | $11.00 | $13.20 |
| A4BAR012 | Alambre recocido Calibre 18 | kg | 0.035500 | $14.52 | $0.52 |
| A4BAR012 | Alambre recocido Calibre 18 | kg | 0.035500 | $14.52 | $0.52 |
| Suma de Material | $27.43 | ||||
| Mano de Obra | |||||
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.005640 | $765.24 | $4.32 |
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.005640 | $765.24 | $4.32 |
| Suma de Mano de Obra | $8.63 | ||||
| Costo Directo | $36.06 |