| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A-4 | PLANTILLA DE CONCRETO F'C=100 KG/CM2, DE 5 CM DE ESPESOR. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCR01 | CONCRETO PREMEZ F'C=100 | M3 | 0.050000 | $710.00 | $35.50 |
| CONCR01 | CONCRETO PREMEZ F'C=100 | M3 | 0.050000 | $710.00 | $35.50 |
| Suma de Material | $71.00 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.040000 | $765.24 | $30.61 |
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.040000 | $765.24 | $30.61 |
| Suma de Mano de Obra | $61.22 | ||||
| Costo Directo | $132.22 |