| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A-12 | MURO DE CONCRETO F'C=200 KG/CM2, DE 20 CM. DE ESPESOR, DE HASTA 1.00 M. DE ALTURA, REFORZADO CON DOBLE PARRILLA DE 3/8", PARA CONTENCION DE RELLENOS Y EN DESNIVELES DE PISO. INCLUYE: ZAPATA DE 0.80 M. DE ANCHO, Y 20 CM. DE ESPESOR CON DOBLE PARRILLA DE 3/8". | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 200 | CONCRETO PREMEZCLADO DE F?C=200 KG/CM2 | M3 | 0.378000 | $910.00 | $343.98 |
| ACERO VARIOS D | ACERO DE REFUERZO DE DIFERENTES DIAMETROS | KG | 22.000000 | $11.00 | $242.00 |
| MADERAPINO3A | MADERA DE PINO DE 3 ERA. EN EN PIE TABLON | PT | 3.546000 | $7.50 | $26.60 |
| CIMBRAPLAY16 MM | CIMBRAPLAY DE 16MM EN M2 | M2 | 0.800000 | $95.00 | $76.00 |
| MOÑOSDE20CMS | MOÑOS PARA CIMBRA DE 20 CMS | pieza | 2.300000 | $7.00 | $16.10 |
| A4BAR012 | Alambre recocido Calibre 18 | kg | 0.100000 | $14.52 | $1.45 |
| CLAVO | CLAVO EN KG | KG | 0.100000 | $13.00 | $1.30 |
| Suma de Material | $707.43 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.201000 | $765.24 | $153.81 |
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.100000 | $765.24 | $76.52 |
| CUAD OC 11 | (1 Of. Carpintero O.N. + 1 Ayud.) | jor | 0.220000 | $765.24 | $168.35 |
| Suma de Mano de Obra | $398.69 | ||||
| Costo Directo | $1,106.12 |