| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A-7 | CONCRETO F'C=250KG/CM2 EN ZAPATAS, TRABES, Y DADOS, DE CIMENTACION. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCR04. | CONCRETO PREMEZCLADO F'C=250 10-13 | M3 | 1.040000 | $1,200.00 | $1,248.00 |
| CONCR04. | CONCRETO PREMEZCLADO F'C=250 10-13 | M3 | 1.040000 | $1,200.00 | $1,248.00 |
| BOMBA/CONCRETO | BOMBA PARA CONCRETO | M3 | 0.500000 | $130.00 | $65.00 |
| BOMBA/CONCRETO | BOMBA PARA CONCRETO | M3 | 0.500000 | $130.00 | $65.00 |
| CURACRETO | CURACRETO | LT | 0.600000 | $18.85 | $11.31 |
| CURACRETO | CURACRETO | LT | 0.600000 | $18.85 | $11.31 |
| AGREGADO-003 | AGUA permisos y licencias | M3 | 0.040000 | $5.00 | $0.20 |
| AGREGADO-003 | AGUA permisos y licencias | M3 | 0.040000 | $5.00 | $0.20 |
| Suma de Material | $2,649.02 | ||||
| Mano de Obra | |||||
| CUAD OC 42 | 1 Of: Albañil + 2 Ayud.) | jor | 0.120000 | $1,087.60 | $130.51 |
| CUAD OC 42 | 1 Of: Albañil + 2 Ayud.) | jor | 0.120000 | $1,087.60 | $130.51 |
| OC 18 AYUDANTE | AYUDANTE DE OFICIAL | Jor | 0.120000 | $307.01 | $36.84 |
| OC 18 AYUDANTE | AYUDANTE DE OFICIAL | Jor | 0.120000 | $307.01 | $36.84 |
| Suma de Mano de Obra | $334.71 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR. | HERRAMIENTA MENOR | (%)mo | 0.020000 | $0.00 | $0.00 |
| HERRAMIENTA MENOR. | HERRAMIENTA MENOR | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| C.F. VIBRADOR CONCRE | VIBRADOR | HR | 0.791000 | $11.90 | $9.41 |
| C.F. VIBRADOR CONCRE | VIBRADOR | HR | 0.791000 | $11.90 | $9.41 |
| Suma de Equipo | $18.83 | ||||
| Costo Directo | $3,002.55 |