| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-4 | FIRME DE CONCRETO DE 15 CM. DE ESPESOR REF. CON MALLA 6X6-6/6. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCR04. | CONCRETO PREMEZCLADO F'C=250 10-13 | M3 | 0.150000 | $1,200.00 | $180.00 |
| MALLA 66/100 | MALLA ELECTROSOLDADA 66 10/10 EN M2 | M2 | 1.100000 | $26.00 | $28.60 |
| A4BAR012 | Alambre recocido Calibre 18 | kg | 0.010000 | $14.52 | $0.15 |
| ACERO VARIOS D | ACERO DE REFUERZO DE DIFERENTES DIAMETROS | KG | 0.200000 | $11.00 | $2.20 |
| CIMBRAMETALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.014300 | $80.10 | $1.15 |
| AGREGADO-003 | AGUA permisos y licencias | M3 | 0.021000 | $5.00 | $0.11 |
| Suma de Material | $212.20 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | (1 Of. Albañil + 5 Peones) | jor | 0.035000 | $2,054.68 | $71.91 |
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.005500 | $765.24 | $4.21 |
| Suma de Mano de Obra | $76.12 | ||||
| Equipo | |||||
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $212.48 | $0.76 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.015000 | $167.18 | $2.51 |
| Suma de Equipo | $3.27 | ||||
| Costo Directo | $291.58 |