| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-9 | PRETIL DE TRABE EXTREMO PARA RECIBIR TECHO TIPO WONDER. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 200 | CONCRETO PREMEZCLADO DE F?C=200 KG/CM2 | M3 | 0.300000 | $910.00 | $273.00 |
| ACERO VARIOS D | ACERO DE REFUERZO DE DIFERENTES DIAMETROS | KG | 25.000000 | $11.00 | $275.00 |
| Suma de Material | $548.00 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.100000 | $765.24 | $76.52 |
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.130000 | $765.24 | $99.48 |
| CUAD OC 11 | (1 Of. Carpintero O.N. + 1 Ayud.) | jor | 0.180000 | $765.24 | $137.74 |
| Suma de Mano de Obra | $313.75 | ||||
| Concepto | |||||
| A-5 | CIMBRA EN ZAPATAS Y DADOS DE CIMENTACION. | M2 | 2.000000 | $147.19 | $294.38 |
| Suma de Concepto | $294.38 | ||||
| Costo Directo | $1,156.13 |