| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ,,..,,..,, | Faldon de tablaroca de 1.20 mts | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABLAROCA FIBERCODE | TABLAROCA MOD. FIRECODE-C DE 1/2" DE ESPESOR (9.40 KG./M2.) | m2 | 1.342000 | $26.03 | $34.93 |
| CAN-AMA-001 | CANAL METALICO USG 410 CAL. 26 | ml | 1.098000 | $8.52 | $9.35 |
| POST-MET-001 | POSTE METALICO USG 410 CAL. 26 | ml | 2.440000 | $11.47 | $27.99 |
| ALAMBRE GALVANIZADO | ALAMBRE GALVANIZADO CAL. 14 | kg | 0.427000 | $17.90 | $7.64 |
| PERFACINTA | PERFACINTA | ml | 2.684000 | $0.30 | $0.81 |
| REDIMIX | REDIMIX | kg | 2.196000 | $4.13 | $9.07 |
| TORNILLO S-1 | TORNILLOS S-1 | pieza | 29.280000 | $0.05 | $1.46 |
| FULMINANTE VERDE | FULMINANTE VERDE | pieza | 2.440000 | $1.38 | $3.37 |
| ANCLAS | ANCLAS HILTI | pieza | 2.440000 | $5.50 | $13.42 |
| Suma de Material | $108.04 | ||||
| Mano de Obra | |||||
| CUADRILLA -25 | (1 OFICIAL DE TABLAROCA + 1 AYUDANTE) | jor | 0.110910 | $867.29 | $96.19 |
| Suma de Mano de Obra | $96.19 | ||||
| Auxiliar | |||||
| 03-7022 | TORRE DE TRABAJO DE 0.00 A 4.00 MTS. DE ALTURA CON RUEDAS | R/D | 0.222040 | $26.02 | $5.78 |
| Suma de Auxiliar | $5.78 | ||||
| Costo Directo | $210.01 |