| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C40A0108 | SUMINISTRO Y COLOCACION DE CIMBRA EN LOSA | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.500000 | $8.50 | $12.75 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.260000 | $8.50 | $2.21 |
| 1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 2.040000 | $6.50 | $13.26 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | kg | 0.350000 | $13.07 | $4.57 |
| 0950-05 | DIESEL | litro | 0.700000 | $7.50 | $5.25 |
| 1900-25 | TARIMA PARA CIMBRA EN MADERA DE PINO DE 3A. DE 1.00 X 0.50 M | PZA | 0.366600 | $16.94 | $6.21 |
| Suma de Material | $44.25 | ||||
| Mano de Obra | |||||
| 02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | jor | 0.132580 | $872.69 | $115.70 |
| Suma de Mano de Obra | $115.70 | ||||
| Costo Directo | $159.96 |