| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C90D0201 | SUMINISTRO E INSTALACIÓN DE FALSO PLAFOND DE TABLAROCA | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABLAROCA BLANCA | TABLAROCA DE YESO | m2 | 1.100000 | $28.38 | $31.22 |
| ALAMBRE GALVANIZADO | ALAMBRE GALVANIZADO CAL. 14 | kg | 0.120000 | $17.90 | $2.15 |
| CANALETA DE CARGA | CANALETA DE CARGA USG CAL. 22 | ml | 1.300000 | $10.45 | $13.59 |
| CANAL LISTON | CANAL LISTON USG CAL. 26 | ml | 2.000000 | $9.18 | $18.36 |
| ANGULO D AMARRE | ANGULO DE AMARRE | ml | 0.250000 | $11.53 | $2.88 |
| TORNILLO S-1 | TORNILLOS S-1 | pieza | 12.000000 | $0.05 | $0.60 |
| PERFACINTA | PERFACINTA | ml | 1.080000 | $0.30 | $0.32 |
| REDIMIX | REDIMIX | kg | 1.500000 | $4.13 | $6.20 |
| ANCLAS | ANCLAS HILTI | pieza | 1.500000 | $5.50 | $8.25 |
| FULMINANTE VERDE | FULMINANTE VERDE | pieza | 1.500000 | $1.38 | $2.07 |
| Suma de Material | $85.63 | ||||
| Mano de Obra | |||||
| CUADRILLA -25 | (1 OFICIAL DE TABLAROCA + 1 AYUDANTE) | jor | 0.150000 | $867.29 | $130.09 |
| Suma de Mano de Obra | $130.09 | ||||
| Auxiliar | |||||
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.050000 | $21.12 | $1.06 |
| Suma de Auxiliar | $1.06 | ||||
| Costo Directo | $216.78 |