| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| C30B0201 | Suministro y colocaci贸n de pavimento hidraulico MR=40 kg/cm2 de 20 cms de espesor con fibra de polipropileno a razon de 0.9 kg/M3 | m2 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | ton | 0.000500 | $1,700.00 | $0.85 |
| FIB-PROP-001 | Fibra de Propileno | kg | 1.000000 | $22.68 | $22.68 |
| AIGFE030 | Cimbrafest 19 lt | pza | 0.000900 | $355.30 | $0.32 |
| CONCRETO MR 40 | CONCRETO PREMEZCLADO MR-40 KG/CM2 | M3 | 0.210000 | $1,020.00 | $214.20 |
| AIBFE125 | Festerlith 1510 n 200 lt | pza | 0.001600 | $2,800.95 | $4.48 |
| AIBFE150 | Festermix 19 lt | pza | 0.017700 | $354.31 | $6.27 |
| Suma de Material | $248.80 | ||||
| Mano de Obra | |||||
| 02-0010 | CUADRILLA No 1 ( 1 PEON ) | jor | 0.028500 | $387.07 | $11.03 |
| Suma de Mano de Obra | $11.03 | ||||
| Equipo | |||||
| HEQRGV001 | Regla vibratoria con motor a gasolina de 8h.p. mca. whiteman mod. l7500 | hora | 0.050000 | $51.11 | $2.56 |
| Suma de Equipo | $2.56 | ||||
| Auxiliar | |||||
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.045900 | $50.00 | $2.30 |
| Suma de Auxiliar | $2.30 | ||||
| Concepto | |||||
| B10025A005 | Cimbra metalica troquelada 305x15cm calibre 14 para pavimento | m2 | 0.190500 | $54.89 | $10.46 |
| A15010F025 | Vaciado, colado, vibrado cimentacion | m3 | 0.210000 | $123.13 | $25.86 |
| A15020A675 | Curado superficies concreto | m2 | 1.020000 | $10.06 | $10.26 |
| Suma de Concepto | $46.58 | ||||
| Costo Directo | $311.26 |