| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C40A0107 | SUMINISTRO Y COLOCACION DE CIMBRA APARENTE | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.500000 | $8.50 | $12.75 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.110000 | $8.50 | $9.44 |
| 1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 2.070000 | $6.50 | $13.46 |
| 1900-30 | CHAFLAN DE MADERA DE PINO DE 3A. DE 1" | M | 1.100000 | $3.50 | $3.85 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | kg | 0.210000 | $13.07 | $2.74 |
| 0082-05 | ALAMBRE RECOCIDO NO. 16 | kg | 0.080000 | $10.20 | $0.82 |
| 0950-05 | DIESEL | litro | 0.057400 | $7.50 | $0.43 |
| 1900-80 | TRIPLAY DE PINO DE 16 MM 1 CARA | HOJA | 0.057400 | $325.00 | $18.66 |
| Suma de Material | $62.14 | ||||
| Mano de Obra | |||||
| 02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | jor | 0.166667 | $872.69 | $145.45 |
| Suma de Mano de Obra | $145.45 | ||||
| Costo Directo | $207.58 |