| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C90D0101 | SUMINISTRO E INSTALACIÓN DE MURO DE TABLAROCA NORMAL CON BASTIDOR METÁLICO A 2 CARAS | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABLAROCA | TABLAROCA DE 1/2" DE ESPESOR | m2 | 2.200000 | $26.03 | $57.27 |
| CAN-AMA-001 | CANAL METALICO USG 410 CAL. 26 | ml | 0.900000 | $8.52 | $7.67 |
| POST-MET-001 | POSTE METALICO USG 410 CAL. 26 | ml | 2.000000 | $11.47 | $22.94 |
| ALAMBRE GALVANIZADO | ALAMBRE GALVANIZADO CAL. 14 | kg | 0.350000 | $17.90 | $6.27 |
| PERFACINTA | PERFACINTA | ml | 4.400000 | $0.30 | $1.32 |
| REDIMIX | REDIMIX | kg | 3.600000 | $4.13 | $14.87 |
| TORNILLO S-1 | TORNILLOS S-1 | pieza | 24.000000 | $0.05 | $1.20 |
| FULMINANTE VERDE | FULMINANTE VERDE | pieza | 2.000000 | $1.38 | $2.76 |
| ANCLAS | ANCLAS HILTI | pieza | 2.000000 | $5.50 | $11.00 |
| Suma de Material | $125.29 | ||||
| Mano de Obra | |||||
| CUADRILLA -25 | (1 OFICIAL DE TABLAROCA + 1 AYUDANTE) | jor | 0.090909 | $867.29 | $78.84 |
| Suma de Mano de Obra | $78.84 | ||||
| Herramienta | |||||
| ELEV-001 | ELEVACION DE MATERIALES | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| 03-7022 | TORRE DE TRABAJO DE 0.00 A 4.00 MTS. DE ALTURA CON RUEDAS | R/D | 0.182000 | $26.02 | $4.74 |
| Suma de Auxiliar | $4.74 | ||||
| Costo Directo | $208.87 |