| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CBEH-036 | SOPORTERIA | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAQ-SCI-1/4" | TAQUETE TIPO SCI DE 1/4" | PZA | 20.000000 | $0.32 | $6.40 |
| TAQ-SCI-3/8" | TAQUETE TIPO SCI DE 3/8" | PZA | 40.000000 | $0.36 | $14.40 |
| TUERCA-1/4-GALV | TUERCA EXAGONAL GALVANIZADA DE 1/4" | PZA | 120.000000 | $0.36 | $43.20 |
| TUERCA-3/8-GALV | TUERCA EXAGONAL GALVANIZADA DE 3/8" | PZA | 180.000000 | $0.43 | $77.40 |
| ARAND-GALV-1/4" | ARANDELA PLANA GALVANIZADA DE 1/4" | PZA | 120.000000 | $0.09 | $10.80 |
| ARAND-GALV-3/8" | ARANDELA PLANA GALVANIZADA DE 3/8" | PZA | 180.000000 | $0.14 | $25.20 |
| MORDAZA-JST-1/4 | MORDAZA DE 1/4" PARA APLICACION EN JOIST , MARCA CLEVIS | PZA | 30.000000 | $20.70 | $621.00 |
| MORDAZA-JST-3/8 | MORDAZA DE 3/8" PARA APLICACION EN JOIST , MARCA CLEVIS | PZA | 65.000000 | $30.60 | $1,989.00 |
| VARILL-ROSC1/4" | VARILLA ROSCADA GALVANIZADA ( ESPARRAGO ) DE 1/4" X 3 METROS DE LARGO | PZA | 8.000000 | $29.34 | $234.72 |
| VARILL-ROSC3/8" | VARILLA ROSCADA GALVANIZADA ( ESPARRAGO ) DE 3/8" X 3 METROS DE LARGO | PZA | 15.000000 | $33.84 | $507.60 |
| UNICANAL4X4 | UNICANAL DE 4 X 4 CMS ( DE 3.05 MTS. ) | PZA | 12.000000 | $160.20 | $1,922.40 |
| ABRAZPERA101 | ABRAZADERA GALVANIZADA TIPO PERA DE 101MM | PZA | 12.000000 | $16.74 | $200.88 |
| ABRAZPERA75 | ABRAZADERA GALVANIZADA TIPO PERA DE 75MM | PZA | 28.000000 | $7.83 | $219.24 |
| ABRAZPERA51 | ABRAZADERA GALVANIZADA TIPO PERA DE 51MM | PZA | 35.000000 | $3.15 | $110.25 |
| ABRAZPERA38 | ABRAZADERA GALVANIZADA TIPO PERA DE 38MM | PZA | 12.000000 | $3.06 | $36.72 |
| ABRAZTIPOU51 | ABRAZADERA GALVANIZADA TIPO U DE 51MM | PZA | 10.000000 | $6.03 | $60.30 |
| ABRAZTIPOU38 | ABRAZADERA GALVANIZADA TIPO U DE 38MM | PZA | 8.000000 | $4.59 | $36.72 |
| ABRAZTIPOU75 | ABRAZADERA GALVANIZADA TIPO U DE 75MM | PZA | 6.000000 | $7.47 | $44.82 |
| Suma de Material | $6,161.05 | ||||
| Mano de Obra | |||||
| CUADRILLA INST. 13 | Cuadrilla de soldadores (soldador + ayudante) | Jor | 2.248554 | $1,023.46 | $2,301.31 |
| CUADRILLA INST. 07 | Cuadrilla 2 peones (2 peones: acarreo, ranuras, excavacion) | Jor | 1.499033 | $855.83 | $1,282.92 |
| Suma de Mano de Obra | $3,584.22 | ||||
| Auxiliar | |||||
| ANDAMIO | ANDAMIO metalicos | DIA | 1.499033 | $16.57 | $24.84 |
| Suma de Auxiliar | $24.84 | ||||
| Costo Directo | $9,770.11 |