| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.1.16 | Construccion de Registros para valvulas | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA2026 | CALHIDRA | KG | 0.250000 | $0.81 | $0.20 |
| MA2048 | CURACRETO ROJO | LT | 3.500000 | $7.52 | $26.32 |
| MA2100 | MADERA DE PINO DE 3A PARA CIMBRA | PT | 2.200000 | $9.20 | $20.24 |
| MA465 | MARCO PARA REGISTRO DE ANGULO DE 2" X 1/8" | PZA | 1.000000 | $275.00 | $275.00 |
| Suma de Material | $321.76 | ||||
| Mano de Obra | |||||
| MO020 | TOPOGRAFO | JOR | 0.050000 | $643.30 | $32.17 |
| MO005 | CADENERO | JOR | 0.050000 | $390.59 | $19.53 |
| Suma de Mano de Obra | $51.69 | ||||
| Herramienta | |||||
| %MO116 | HERRAMIENTA MANUAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| %MO118 | EQUIPO SEGURIDAD PERSONAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQTC25 | ESTACION TOTAL MARCA FOIF | HORA | 0.400000 | $15.06 | $6.02 |
| Suma de Equipo | $6.02 | ||||
| Auxiliar | |||||
| CIMBRA EN MUROS | BASICO DE CIMBRA | M2 | 7.400000 | $69.25 | $512.45 |
| BAEXCAV | BASICO DE EXCAVACIONES EN MAT A Y B | M3 | 1.990000 | $35.12 | $69.89 |
| BASRELLZANJA | BASICO PARA RELLENO EN ZANJA | M3 | 0.350000 | $61.78 | $21.62 |
| BAACEROREF | BASICO SUM HABIL Y COLOC ACERO REFZO | TON | 0.072000 | $16,947.57 | $1,220.23 |
| BACONC100 | ELABORACION CONCRETO 100 KG/CM2 | M3 | 0.100000 | $886.71 | $88.67 |
| ELAB CON 200 | ELABORACION CONCRETO F'c=200KG/CM2 | M3 | 0.400000 | $1,188.13 | $475.25 |
| BASCONC250 | ELABORACION CONCRETO F'c=250KG/CM2 | M3 | 0.900000 | $1,214.95 | $1,093.46 |
| Suma de Auxiliar | $3,481.56 | ||||
| Costo Directo | $3,861.05 |