| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.1.4 | Alcantarilla de polietileno de alta densidad 48 plg | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA2173 | TUBO POLIETILENO ALTA DENSIDAD DE 48" DIAM | M | 1.000000 | $2,180.00 | $2,180.00 |
| MA2013 | ARENA DE BANCO | M3 | 0.100000 | $145.00 | $14.50 |
| MA2026 | CALHIDRA | KG | 0.120000 | $0.81 | $0.10 |
| MA2079 | HILO CAÑAMO | PZA | 0.000971 | $10.30 | $0.01 |
| MA2100 | MADERA DE PINO DE 3A PARA CIMBRA | PT | 0.005435 | $9.20 | $0.05 |
| Suma de Material | $2,194.66 | ||||
| Mano de Obra | |||||
| MO020 | TOPOGRAFO | JOR | 0.002063 | $643.30 | $1.33 |
| MO005 | CADENERO | JOR | 0.002910 | $390.59 | $1.14 |
| MO001 | AYUDANTE GENERAL | JOR | 0.065000 | $308.92 | $20.08 |
| MO004 | CABO DE OFICIOS | JOR | 0.004787 | $852.29 | $4.08 |
| Suma de Mano de Obra | $26.62 | ||||
| Herramienta | |||||
| %MO116 | HERRAMIENTA MANUAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| %MO118 | EQUIPO SEGURIDAD PERSONAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQTC42 | NIVEL DE TOPOGRAFIA MCA. K+E | HORA | 0.009107 | $5.49 | $0.05 |
| EQTC15 | COMPACTADOR MANUAL DE PLACA VIBRATORIA | HORA | 0.350000 | $103.62 | $36.27 |
| EQTC06 | CAMION CON HIAB 8.0 Tons. | HR | 0.040000 | $549.36 | $21.97 |
| Suma de Equipo | $58.29 | ||||
| Auxiliar | |||||
| BAEXCAV | BASICO DE EXCAVACIONES EN MAT A Y B | M3 | 4.000000 | $35.12 | $140.48 |
| Suma de Auxiliar | $140.48 | ||||
| Costo Directo | $2,420.05 |