| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.3.1 | Construccion de pavimento flexible de 5 cm de espesor | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA2026 | CALHIDRA | KG | 0.197531 | $0.81 | $0.16 |
| MA2079 | HILO CAÑAMO | PZA | 0.000971 | $10.30 | $0.01 |
| MA2100 | MADERA DE PINO DE 3A PARA CIMBRA | PT | 0.008696 | $9.20 | $0.08 |
| Suma de Material | $0.25 | ||||
| Mano de Obra | |||||
| MO020 | TOPOGRAFO | JOR | 0.003422 | $643.30 | $2.20 |
| MO005 | CADENERO | JOR | 0.004862 | $390.59 | $1.90 |
| MO001 | AYUDANTE GENERAL | JOR | 0.014019 | $308.92 | $4.33 |
| MO004 | CABO DE OFICIOS | JOR | 0.000690 | $852.29 | $0.59 |
| Suma de Mano de Obra | $9.02 | ||||
| Herramienta | |||||
| %MO116 | HERRAMIENTA MANUAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| %MO118 | EQUIPO SEGURIDAD PERSONAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQTC42 | NIVEL DE TOPOGRAFIA MCA. K+E | HORA | 0.001821 | $5.49 | $0.01 |
| Suma de Equipo | $0.01 | ||||
| Auxiliar | |||||
| BASE HIDRAU | BASE HIDRAULICA DE 20 CMS DE ESPESOR | M2 | 1.000000 | $45.81 | $45.81 |
| PAVIMENTO | BASICO PAVIMENTO 5 CMS ESPESOR | M2 | 1.000000 | $93.54 | $93.54 |
| BARIEGOSELLO | BASICO RIEGO DE SELLO | M2 | 1.000000 | $15.21 | $15.21 |
| BAPINTURA | BASICO DE PINTURA EN PAVIMENTOS | M2 | 1.000000 | $1.81 | $1.81 |
| Suma de Auxiliar | $156.37 | ||||
| Costo Directo | $165.65 |