| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 3.1.14 | Construcci贸n de canal de descarga tipo trapezoidal | M |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA2026 | CALHIDRA | KG | 0.123457 | $0.81 | $0.10 |
| MA2079 | HILO CA脩AMO | PZA | 0.000971 | $10.30 | $0.01 |
| MA2100 | MADERA DE PINO DE 3A PARA CIMBRA | PT | 0.005435 | $9.20 | $0.05 |
| MA2102 | MALLA DE ACERO ELECTROSOLDADA CAL 66/6-6 | M2 | 1.100000 | $32.00 | $35.20 |
| Suma de Material | $35.36 | ||||
| Mano de Obra | |||||
| MO020 | TOPOGRAFO | JOR | 0.002063 | $643.30 | $1.33 |
| MO005 | CADENERO | JOR | 0.002910 | $390.59 | $1.14 |
| MO004 | CABO DE OFICIOS | JOR | 0.005000 | $852.29 | $4.26 |
| MO009 | OFICIAL ALBANIL | JOR | 0.025000 | $537.98 | $13.45 |
| MO001 | AYUDANTE GENERAL | JOR | 0.050000 | $308.92 | $15.45 |
| Suma de Mano de Obra | $35.62 | ||||
| Herramienta | |||||
| %MO118 | EQUIPO SEGURIDAD PERSONAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| %MO116 | HERRAMIENTA MANUAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQTC42 | NIVEL DE TOPOGRAFIA MCA. K+E | HORA | 0.009107 | $5.49 | $0.05 |
| EQTC12 | CAMIONETA DE 3.5 TON. CON REDILAS | HR | 0.006753 | $281.72 | $1.90 |
| Suma de Equipo | $1.95 | ||||
| Auxiliar | |||||
| BAEXCAV | BASICO DE EXCAVACIONES EN MAT A Y B | M3 | 1.650000 | $35.12 | $57.95 |
| CIMBRA EN MUROS | BASICO DE CIMBRA | M2 | 0.045498 | $69.25 | $3.15 |
| ELAB CONC 150 | ELABORACION CONCRETO 150 KG/CM2 | M3 | 0.152000 | $1,009.48 | $153.44 |
| Suma de Auxiliar | $214.54 | ||||
| Costo Directo | $287.47 |