| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 1.2.7 | Rehabilitaci贸n de caminos de acceso | M2 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA2006 | AGUA | M3 | 0.008250 | $28.20 | $0.23 |
| Suma de Material | $0.23 | ||||
| Mano de Obra | |||||
| MO004 | CABO DE OFICIOS | JOR | 0.000200 | $852.29 | $0.17 |
| MO001 | AYUDANTE GENERAL | JOR | 0.002000 | $308.92 | $0.62 |
| Suma de Mano de Obra | $0.79 | ||||
| Herramienta | |||||
| %MO116 | HERRAMIENTA MANUAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| %MO118 | EQUIPO SEGURIDAD PERSONAL | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQTC39 | MOTOCONFORMADORA CAT 14H, 215 HP CATERPILLAR | HORA | 0.003600 | $516.24 | $1.86 |
| EQTC08 | CAMION PIPA 10M3 INTERNATIONAL | HR | 0.004800 | $266.12 | $1.28 |
| EQTC58 | VIBROCOMPACTADOR DYNAPAC CA 280, 110 HP | HORA | 0.026000 | $312.60 | $8.13 |
| Suma de Equipo | $11.26 | ||||
| Costo Directo | $12.28 |