| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2. | TRAZO Y NIVELACIÓN. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PREL | HILO DE PLASTICO PARA TRAZO CAL. 10 | PZA | 0.000637 | $14.73 | $0.01 |
| MAD02 | BARROTE DE 2" X 4" PINO DE 2ª | PT | 0.001372 | $11.45 | $0.02 |
| CAL1 | CAL HIDRATADA | TON | 0.000029 | $519.47 | $0.02 |
| Suma de Material | $0.04 | ||||
| Mano de Obra | |||||
| ZCUAD13 | CUADRILLA (1 AUXILIAR DE TOPOGRAFO + 1 ESTADALERO) | JOR | 0.001049 | $1,206.14 | $1.27 |
| ZCUAD | CUADRILLA (1 PEON) | JOR | 0.000813 | $476.07 | $0.39 |
| Suma de Mano de Obra | $1.65 | ||||
| Equipo | |||||
| 18MAQ | NIVEL DIGITAL MARKA LEICA DS3210 | Hora | 0.023110 | $1.21 | $0.03 |
| 17MAQ | ESTACION TOTAL LEICA TC 407 | Hora | 0.004596 | $11.60 | $0.05 |
| 16MAQ | CAMIONETA SILVERADO CHEVROLET 3500 CON CABINA | Hora | 0.000255 | $133.09 | $0.03 |
| Suma de Equipo | $0.12 | ||||
| Costo Directo | $1.81 |