| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 32006 | EMBOQUILLADO EN MUROS A PLOMO Y REGLA CON MORTERO CEM-CAL-ARENA 1:2:6, INCLUYE PERFILADO DE DOS ARISTAS. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| 2MOCU-005 | Cuadrilla No 5 (1 Albañíl + 1 Ayudante general ) | Jor | 0.125000 | $888.17 | $111.02 |
| 2MOCU-005 | Cuadrilla No 5 (1 Albañíl + 1 Ayudante general ) | Jor | 0.125000 | $888.17 | $111.02 |
| Suma de Mano de Obra | $222.04 | ||||
| Auxiliar | |||||
| 03-0290 | MORTERO CEMENTO-CALHIDRA-ARENA 1:2:6 | m3 | 0.046000 | $992.74 | $45.67 |
| 03-0290 | MORTERO CEMENTO-CALHIDRA-ARENA 1:2:6 | m3 | 0.046000 | $992.74 | $45.67 |
| OC-AUX3 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | M3 | 0.004000 | $64.90 | $0.26 |
| OC-AUX3 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | M3 | 0.004000 | $64.90 | $0.26 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.125000 | $21.92 | $2.74 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.125000 | $21.92 | $2.74 |
| Suma de Auxiliar | $97.33 | ||||
| Costo Directo | $319.37 |