| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| LOSA-014 | LOSA 1100 VIGUETA Y BOVEDILLA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CASETON | CASETON STIROLITE 50X50X30 CMS | pza | 2.352000 | $45.00 | $105.84 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 1.100000 | $10.12 | $11.13 |
| VIGUETA VARIAS MED. | VIGUETAS DE ALMA ABIERTA VARIAS MEDIDAS FR 14 CMS. | PZA | 2.780000 | $16.36 | $45.48 |
| Suma de Material | $162.45 | ||||
| Mano de Obra | |||||
| CUAD OC 12 | (1 Of. Albanil + 1 Peón) | JOR | 0.500000 | $673.86 | $336.93 |
| Suma de Mano de Obra | $336.93 | ||||
| Auxiliar | |||||
| CONCRETO BOMB 250 | CONCRETO PREMEZCLADO FC=250 KG/CM2 BOMBEABLE | M3 | 0.085000 | $1,417.77 | $120.51 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 8.000000 | $14.89 | $119.12 |
| Suma de Auxiliar | $239.63 | ||||
| Costo Directo | $739.01 |