| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-08 | CIMIENTO CORRIDO INTERIOR Y COLINDANTE F'C= 300 KG/CM2 PUZOLANICO | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IMPERM. INTEGRAL | IMPERMEABILIZANTE INTEGRAL | M3 | 0.180000 | $80.00 | $14.40 |
| Suma de Material | $14.40 | ||||
| Auxiliar | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 1.200000 | $170.37 | $204.44 |
| CONCRETO BOMB 300 | CONCRETO PREMEZCLADO FC=300 KG/CM2 BOMBEABLE | M3 | 0.180000 | $1,377.66 | $247.98 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 10.710000 | $14.89 | $159.47 |
| Suma de Auxiliar | $611.89 | ||||
| Costo Directo | $626.29 |