| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-29 | PISO DE CONCRETO ESTACIONAMIENTO EXTERIOR | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO MR-40 | CONCRETO PROFESIONAL MR = 40 KG/CM2 MODULO DE RUPTURA, ESPECIAL PARA PAVIMENTOS CON RESISTENCIA A LA FLEXION, DE 15 CMS. DE ESPESOR | m3 | 0.157500 | $1,200.00 | $189.00 |
| FIBRA FEST | FIBRA DE POLIPROPILENO PARA CONCRETO | kg | 0.180000 | $85.76 | $15.44 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 7.020000 | $7.00 | $49.14 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.035000 | $14.00 | $0.49 |
| MEMBRANA DE PARAF. | MEMBRANA DE PARAFINA BASE AGUA COLOR BLANCO | lit | 0.075000 | $16.96 | $1.27 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.014300 | $8.00 | $0.11 |
| POLIETILENOCAL 600 | POLIETILENO EN ROLLO | M2 | 0.012500 | $9.42 | $0.12 |
| AGUA | AGUA ACARREO INTERNO | M3 | 0.021000 | $40.00 | $0.84 |
| PEINE METALICO | PEINE METALICO PARA ACABADO DE CONCRETO | PZA | 0.000500 | $857.58 | $0.43 |
| Suma de Material | $256.84 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.031250 | $1,466.04 | $45.81 |
| Suma de Mano de Obra | $45.81 | ||||
| Equipo | |||||
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $195.61 | $0.70 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.016665 | $104.98 | $1.75 |
| Suma de Equipo | $2.45 | ||||
| Costo Directo | $305.10 |