| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| DREN-06 | REGISTRO DE DESCARGA GENERAL DE 1.00*1.00 | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-250 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2, ELABORADO CON CEMENTO CPP-30R-RS | M3 | 1.130800 | $810.00 | $915.95 |
| ANGULO 1 3/4 X 3/16 | ANGULO DE ACERO DE 1 3/4 X 3/16" | KG | 24.680000 | $9.02 | $222.61 |
| ANGULO 1 1/2 X 3/16 | ANGULO DE ACERO DE 1 1/2" X 3/16" | KG | 18.230000 | $9.02 | $164.43 |
| Suma de Material | $1,303.00 | ||||
| Mano de Obra | |||||
| CUAD OC 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.083333 | $1,766.13 | $147.18 |
| CUAD OC 08 | CUAD. 1.00 HOJALTERO/HERRERO + 1.00 AYUDANTE GENERAL. | JOR | 0.055556 | $699.85 | $38.88 |
| Suma de Mano de Obra | $186.06 | ||||
| Equipo | |||||
| AESMERILADORA | Esmeriladora | HR | 0.130390 | $6.31 | $0.82 |
| AAMAQUINARIA-94 | Soldadora Miller Dimension Mod. 652 | HR | 0.145760 | $29.01 | $4.23 |
| Suma de Equipo | $5.05 | ||||
| Auxiliar | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 11.440000 | $170.37 | $1,949.03 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 67.090000 | $14.89 | $998.97 |
| Suma de Auxiliar | $2,948.00 | ||||
| Costo Directo | $4,442.11 |