| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-05 | Z-3 DE 3.00*2.00 DADO DE 0.55*0.55 PARR # 5 A/C 15 , 16# 6 EN DADOESTRIBOS #3 TRIPLES. F'C = 300 KG/CM2 PUZOLANICO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IMPERM. INTEGRAL | IMPERMEABILIZANTE INTEGRAL | M3 | 3.230000 | $80.00 | $258.40 |
| Suma de Material | $258.40 | ||||
| Auxiliar | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 5.920000 | $170.37 | $1,008.59 |
| CONCRETO BOMB 300 | CONCRETO PREMEZCLADO FC=300 KG/CM2 BOMBEABLE | M3 | 3.230000 | $1,377.66 | $4,449.84 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 195.000000 | $14.89 | $2,903.55 |
| Suma de Auxiliar | $8,361.98 | ||||
| Costo Directo | $8,620.38 |